- Pollution mitigation of Karamana- Killi river
- To develop a model for all the rivers
- Reduce water & vector - borne diseases in the city
- Reduce drinking & bathing water and sewage pollution
- Mitigate flash flood in the city
- Avert people from river pollution activities
Identification of sub projects & action Plan
- Public participation and interaction
- Site inspection
- Media reports
- RITES study report (2013)
- Advise from Committees
Implementation & monitoring
- Technical Committee
- Co-ordination Committee
- Monitoring Committee
- Monitoring cell
KSCSTE - Co-ordination
TRIDA - Implementation
Line Departments & Institutions [Execution] - Irrigation, KWA (Sewage), Minor irrigation, PWD, Home Dept.,City corporation, KSBB, etc.
Year | Budget Estimate | Amount received |
2013-14 | 500 lakh | 466.66 lakh |
2014-15 | 800 lakh | 800 lakh |
2015-16 | 800 lakh | NIL |
Sub-projects undertaken during 2013-14
b) Pump house
c) Pump set
d) Slope Correction
Exn:(Irrigation Dept.)
All works are completed.
Budget Estimate : 50 lakhs
![]() |
![]() |
Slope Correction | Weir with PVC shutters |
![]() |
![]() |
Pump-house | Thiuvallam pump on operation |
![]() |
![]() |
![]() |
New Balikkadavu | New Balikkadavu | Biogas Plant |
![]() |
![]() |
![]() |
Renovation of Balikkadavu work started | Thiruvallam Thode fencing over (a) | Thiruvallam Thode fencing over (b) |
III. Gated Weir at Myladikadavu
Execution: Major irrigation Budget Estimate 22.5 lakhs.Work completed.
![]() |
![]() |
![]() |
Weir at Myladikkadavu | Weir at Myladikkadavu work | completed |
IV. Renovation of Maruthankuzhi Weir
Execution: Major irrigation.Budget Estimate : 25 lakhs.Work Completed
![]() |
![]() |
Maruthankuzhi Weir | Maruthankuzhy weir door to Kochar |
V. Renovation of drains with silt trap at Myladikad
Execution: City corporation.Budget Estimate 52.5 lakhs.Work Completed
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
Thiruvallam NH Bridge Fencing
II. Renovation of Thekkanekkara canal (open canal)- 2.57 kms.
Execution: Major irrigation Budget Estimate 125 lakhs.
d) Chain linked fence at sides of canal & bridges
Work progressing.
![]() |
![]() |
![]() |
![]() |
Thekkanekkara canal after cleaning
![]() |
![]() |
![]() |
Thekkanekkara canal beginning cleaning Thekkanekkara canal poles for fencing Thekkanekkara canal fencing
III. Providing 3 new Sewage pumps at Kuriathy Pumping Station with panel, Transformer, etc
Execution:KWA (Sewage)
Budget Estimate : 160 lakhs
Pumps received. Installation started.
![]() |
![]() |
IV. Sewage pipelines at Thittakudi, Sastri nagar, Siva nagar & Kailas nagar
Execution: KWA (sewage)
Budget Estimate : 190 lakhs.
Two lines completed. Other two lines, work in progress.
![]() |
![]() |
V. Installation of Surveillance Camera at Myladikadavu to Maruthankuzhi
Execution: Home Dept. through KELTRON
Budget Estimate : 63 lakhs
Order issued. Work will start soon by Keltron
VI. Biodiversity Park & protective work of the right bank downstream of Karamana Bridge
Execution: Irrigation
Budget Estimate : 70 lakhs
Major part of the foundation of Bank protection work over. Remaining work resume after rain.
![]() |
![]() |
Biopark at Karamana Biopark at Kalady, Gabion casing
VII. Chain linked fencing on 10 bridges along Killi river
Execution: Major irrigation
Budget Estimate - 70 lakhs
Fabrication work started.
Awareness and Publicity
Execution: KSCSTE Budget Estimate : 17 lakhs
Documentary video - order issue soon.
Awareness Programme - Started, one workshop for public conducted.